64. If a local municipality has not, within 35 days after a project notice was sent to it, issued an authorization that is necessary to carry out a project or if it has informed the public body that the by-laws impeding the issuance of that authorization do not fall under its jurisdiction, the public body may notify a public project declaration to the local municipality.
The declaration must include a brief description of the project and specify its location, the date contemplated for the work to begin and, if the public body has received a notice under section 60, the reasons for which the project is not in conformity with the planning by-laws.
2020, c. 272020, c. 27, s. 64.