31.7.2. The Government or a committee of ministers referred to in section 31.5 may also exempt, from all or part of the environmental impact assessment and review procedure, a project to establish or enlarge a landfill site used in whole or in part as a final disposal site for household garbage collected by or for a municipality if, in the Government’s or committee’s opinion, the situation requires that the project be carried out within a shorter time frame than that required for the application of the procedure.
In such a case, the Government or the committee must issue an authorization for the project and include the conditions, restrictions and prohibitions it considers necessary to protect the environment. The situation that warranted the exemption must also be described in the decision.
The operation period of a landfill site for which such a decision is made may not exceed one year. A decision made under this section may be renewed only once for the same project.
2017, c. 42017, c. 4, s. 211.