144. The authorization holder must ensure that, 90 days after the end of the pipeline construction work, the temporary work areas are restored to a state allowing for the harmonization of the site with the use of the territory.
On request, the Minister may grant an additional period for the restoration if the holder demonstrates the need therefor. The holder must, at least 30 days before the end of the 90-day period, notify the Minister, in writing, of the reasons preventing the restoration within the prescribed period.
1253-2018O.C. 1253-2018, s. 144.