2. An application for authorization under the first paragraph of section 1 shall contain the following:(1) the project objectives;
(2) the project description;
(3) the justification of the project with regard to the objectives;
(4) the project costs;
(5) the project feasibility study;
(6) the list of authorizations required under other laws;
(7) the impact on the rates including a sensitivity analysis;
(8) the impact on the reliability of the electric power transmission system and on the quality of the electric power transmission service or electric power or natural gas distribution service; and
(9) any other solutions contemplated, which must include the information referred to in the preceding paragraphs.