48. The verification of a project report must include a project site visit by the verifier, except if such a visit was carried out for the purposes of a verification conducted during the two preceding reporting periods within the same eligibility period.
The site visit must enable the verifier, in particular, to observe the proper conduct and operation of the project and any change made to the project since the preceding verification. During the site visit, the verifier must be accompanied by the promoter.
In cases where the methane is reclaimed by a person or municipality other than the promoter, the promoter must ensure that the verifier has access to all the equipment, facilities and documentation needed to conduct the verification of the project report in accordance with this Division.
2021-06-11M.O. 2021-06-11, s. 48.