94. The following activities connected with the production, transformation and storage of electricity require authorization pursuant to subparagraph 10 of the first paragraph of section 22 of the Act:(1) the construction and subsequent operation of(a) an electric power control or transformer station or an electricity storage system;
(b) a wind farm or wind generator;
(c) a solar energy facility;
(d) a power station burning fossil fuels;
(e) a hydroelectric power station;
(2) the relocation of an electric power control or transformer station or an electricity storage system;
(3) an increase in the power of a wind farm, facility or power station referred to in one of subparagraphs b to e of paragraph 1.