79.10. After the consultation period concerning the draft by-law, the council of the regional county municipality shall adopt the by-law, with or without changes.
For the purposes of the first paragraph, the consultation period runs until the end of the last of the following days:(1) the day the last resolution transmitted by a municipality pursuant to section 79.4 is received or, failing such a transmission by a municipality, the last day of the period applicable to it under that section;
(2) the day the public meeting is held or, if several are held, the day the last meeting is held, or the last day of the period prescribed in the second paragraph of section 79.5.