38. Within 45 days following the notification of the application, the Commission must give an assessment based solely on whether or not the plan or program contemplated in section 33 or 34 or the by-law contemplated in section 102 is consistent with the objectives of the RCM plan and with the complementary document.
On the issuance of the assessment, a copy of it shall be sent to the municipality that applied for it and to the regional county municipality.
The assessment of conformity rendered by the Commission is binding in that respect on the interested persons. This assessment may, however, include, but only as indications, the suggestions of the Commission with regard to the manner of ensuring the required conformity.
1979, c. 51, s. 38; 1987, c. 102, s. 9; 2002, c. 68, s. 52; 2010, c. 10, s. 110; I.N. 2016-01-01 (NCCP).