148.0.21. No certificate authorizing demolition may be issued by the person designated under paragraph 7 of section 119 before the expiry of 30 days as provided in section 148.0.19 or, if there has been a review under that section, before the council has rendered a decision authorizing the demolition.
Where section 148.0.20.1 applies, no certificate authorizing demolition may be issued before the earlier of the following:
(1)  the date on which the regional county municipality notifies the municipality that it does not intend to avail itself of the power of disallowance provided for in the third paragraph of that section; or
(2)  the expiry of the 90 days provided for in that paragraph.
2005, c. 6, s. 134; 2021, c. 10, s. 110.
148.0.21. No certificate authorizing demolition may be issued by the person designated under paragraph 7 of section 119 before the expiry of 30 days as provided in section 148.0.19 or, if there has been an appeal under that section, before the council has rendered a decision authorizing the demolition.