36. However, in the cases provided for in paragraph d of section 35, the following conditions apply:(a) the installations shall, taking into account all circumstances, be situated as far away as possible from the centre of the agglomeration and at least eight kilometres from the said centre;
(b) lands necessary for such purposes shall be replaced in all cases;
(c) all reasonable efforts shall be made to locate such gas pipelines, oil pipelines and energy transmission lines on Category III or Category II lands, for equal cost.