95. In establishing an indemnity under this subdivision II, the costs are valuated taking into account that the work must be carried out using similar and modern materials equivalent to those of the expropriated immovable or, as applicable, to those of the leased or occupied part of the expropriated immovable, according to current construction standards and according to current development concepts and methods, and taking into account the legal and contractual constraints.
2023, c. 272023, c. 27, s. 95.