6.1. Every contract for the exportation of power and energy by Hydro-Québec under which Hydro-Québec cannot interrupt delivery unilaterally must be submitted to the Government for authorization, which authorization may be given in the cases and subject to the conditions determined by the Government.
Without such authorization, Hydro-Québec may not submit an application under subparagraph 6 of the first paragraph of section 73 of the Act respecting the Régie de l’énergie (chapter R-6.01).
1983, c. 15, s. 38; 1996, c. 61, s. 120.