58. Any civil protection authority in whose area of jurisdiction a major or minor disaster occurred or was apprehended requiring response operations under the authority’s responsibility according to the civil protection plan must, within six months following the emergency, report to the regional authority the date, time, site, nature, probable causes and circumstances of the event and the emergency response and recovery operations conducted.
However, any information whose disclosure would in all likelihood affect judicial proceedings in which the authority, any of the members of its council or a person designated under section 54 has an interest may be reported only once the judgment in the case has become res judicata.