21.48.23. If a debtor considers that the debtor is not required to pay all or part of a sum of money claimed by means of a valid request for payment, the debtor must express refusal to pay within the time determined by government regulation and in compliance with any other terms and conditions determined by such a regulation, such as a requirement to include a description of the work covered by the refusal as well as the grounds justifying and the sum of money corresponding to the refusal.
2022, c. 18, s. 111.