902. The procès-verbal, in addition to the details contained in the plans and specifications, must mention:(1) the works to be done and the delays within which they must be done;
(2) the taxable properties of owners or occupants bound to do the works or to contribute to the cost thereof;
(3) the share of the work to be done by each ratepayer, if the nature of the works allow, in case the work is to be done by the ratepayers themselves;
(4) the extent and area of each lot drained, wholly or in part, by the ditch or watercourse;
(5) the nature and quality of the materials to be used for the underground construction of the covered part of the drain;
(6) the nature, extent and probable cost of the work.