86.2. The Board may, by regulation, prescribe the conditions, manner, and rules according to which a claim may be admitted for compensation out of the fund and out of the security, and in particular prescribe(1) the categories of persons who may benefit from the rights granted by this division;
(2) the categories of contractors who are required to provide security and contribute to the fund;
(3) the categories of buildings, civil engineering structures, facilities and installations covered;
(4) categories of work or cost of work for each category of persons, buildings, civil engineering structures, facilities and installations covered;
(5) the nature of claims, the amount of deductible, the maximum amounts that may be claimed and the other terms or conditions according to which compensation may be paid out of the security and out of the fund;
(6) the maximum total amount of compensation that may be paid out of the security and out of the fund in respect of all claims presented during a fiscal year in respect of the same contractor;
(7) the minimum amount of money needed to defray the operating costs of the fund;
(8) an indicator of the importance of the contractor’s activities and performance which may be used as a basis for establishing contributions and the terms and conditions of payment of such contributions to the fund by a person applying for a licence or the renewal of a licence;
(9) special contributions and the terms and conditions of payment of such contributions to the fund when the amount making up the fund is less than the minimum amount fixed.