153. An opinion to the effect that the agency’s plan is not consistent with the objectives of a land use planning and development plan must include reasons and may contain suggestions by the regional county municipality for ensuring that consistency.
The agency must, within 90 days after receiving the opinion, amend its protection and development plan to ensure that it is consistent with the objectives of the land use planning and development plan.