S-3.1.01, r. 1 - Dam Safety Regulation

Full text
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
Cost of WorkFee
Less than $25,000$1,343
$25,001 to $100,000$1,343 for the first $25,000, plus $40
 for each additional $1,000 or part thereof
$100,001 to $500,000$4,495 for the first $100,000, plus $10
 for each additional $1,000 or part thereof
$500,001 to $1,000,000$8,699 for the first $500,000, plus $4
 for each additional $1,000 or part thereof
$1,000,001 to $10,000,000$10,800 for the first $1,000,000, plus $2
 for each additional $1,000 or part thereof
$10,000,001 to $40,000,000$29,715 for the first $10,000,000, plus $1
 for each additional $1,000 or part thereof
$40,000,001 and up$61,239 for the first $40,000,000, plus
 $0.10 for each additional $1,000 or part thereof
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
Cost of WorkFee
Less than $25,000$1,278
$25,001 to $100,000$1,278 for the first $25,000, plus $40
 for each additional $1,000 or part thereof
$100,001 to $500,000$4,278 for the first $100,000, plus $10
 for each additional $1,000 or part thereof
$500,001 to $1,000,000$8,278 for the first $500,000, plus $4
 for each additional $1,000 or part thereof
$1,000,001 to $10,000,000$10,278 for the first $1,000,000, plus $2
 for each additional $1,000 or part thereof
$10,000,001 to $40,000,000$28,278 for the first $10,000,000, plus $1
 for each additional $1,000 or part thereof
$40,000,001 and up$58,278 for the first $40,000,000, plus
 $0.10 for each additional $1,000 or part thereof
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,201
__________________________________________________________________________

$25,001 to $100,000 $1,201 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,201 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,201 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,201 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,201 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,201 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,170
__________________________________________________________________________

$25,001 to $100,000 $1,170 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,170 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,170 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,170 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,170 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,170 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,155
__________________________________________________________________________

$25,001 to $100,000 $1,155 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,155 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,155 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,155 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,155 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,155 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,135
__________________________________________________________________________

$25,001 to $100,000 $1,135 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,135 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,135 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,135 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,135 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,135 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,116
__________________________________________________________________________

$25,001 to $100,000 $1,116 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,116 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,116 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,116 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,116 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,116 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,107
__________________________________________________________________________

$25,001 to $100,000 $1,107 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,107 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,107 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,107 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,107 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,107 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,099
__________________________________________________________________________

$25,001 to $100,000 $1,099 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,099 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,099 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,099 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,099 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,099 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,087
__________________________________________________________________________

$25,001 to $100,000 $1,087 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,087 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,087 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,087 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,087 for the first $10,000,000, plus $1
for each additional $1,000 or part
thereof
__________________________________________________________________________

$40,000,001 and up $58,087 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,076
__________________________________________________________________________

$25,001 to $100,000 $1,076 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,076 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,076 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,076 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,076 for the first $10,000,000, plus $1
for each additional $1,000 or part thereof
__________________________________________________________________________

$40,000,001 and up $58,076 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,066
__________________________________________________________________________

$25,001 to $100,000 $1,066 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,066 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,066 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,066 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,066 for the first $10,000,000, plus $1
for each additional $1,000 or part thereof
__________________________________________________________________________

$40,000,001 and up $58,066 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.
64. The application processing fee for authorization for the construction or structural alteration of a dam is based on the following table, taking into account the cost estimated by the project engineer to perform the work requiring the authorization:
__________________________________________________________________________

Cost of Work Fee
__________________________________________________________________________

Less than $25,000 $1,040
__________________________________________________________________________

$25,001 to $100,000 $1,040 for the first $25,000, plus $40 for
each additional $1,000 or part thereof
__________________________________________________________________________

$100,001 to $500,000 $4,040 for the first $100,000, plus $10
for each additional $1,000 or part thereof
__________________________________________________________________________

$500,001 to $1,000,000 $8,040 for the first $500,000, plus $4 for
each additional $1,000 or part thereof
__________________________________________________________________________

$1,000,001 to $10,000,000 $10,040 for the first $1,000,000, plus $2
for each additional $1,000 or part thereof
__________________________________________________________________________

$10,000,001 to $40,000,000 $28,040 for the first $10,000,000, plus $1
for each additional $1,000 or part thereof
__________________________________________________________________________

$40,000,001 and up $58,040 for the first $40,000,000, plus
$0.10 for each additional $1,000 or part
thereof
__________________________________________________________________________
The cost of the work includes the engineering fees and costs relating to the plan design and specifications, work supervision, quality control and materials, machinery and labour costs to carry out the dam construction or structural alteration work.
O.C. 300-2002, s. 64.