400. An in-depth verification report establishing the safety of a multistorey garage must contain the following information or documents:(1) the name, signature and business address of the engineer;
(2) a description of the mandate, the documentary review, the observation methods applied and the scope of the verification;
(3) information on the multistorey garage, including its location, age, dimensions, method of construction and load carrying capacity;
(4) the date of the verification work;
(5) the outcome of the verification of all the structural elements of the multistorey garage assessed, including concrete characteristics, the state of corrosion of the reinforcement, and a description of any defects that may contribute to the development of a dangerous condition, along with their causes;
(6) the location of any defects noted during the verification;
(7) a description of the corrective work required to ensure that the multistorey garage remains safe, and the schedule recommended for its implementation;
(8) a summary of the report confirming that the multistorey garage is not in a dangerous condition and, where applicable, that recommendations have been submitted to the owner concerning ways to correct the defects observed that may contribute to the development of a dangerous condition;
(9) appendices containing photographs, drawings and any other relevant information obtained during the in-depth verification, to complete the report.