The daily report must contain all the elements applicable to the declared day, in particular,(1) the number of the geochemical surveying authorization;
(2) the type of surveying conducted;
(3) a description, in chronological order, of the work carried out and the time required to carry out each step of the work;
(4) the numbers of the sampling points and data acquisition modules, their depths and theirs GPS coordinates;
(5) if applicable, the discovery of a natural seepage;
(6) work interruptions and disturbances due in particular to meteorological conditions and technical and operational difficulties, and their duration;
(7) the operational problems encountered and the corrective measures taken or planned; and
(8) any other information or document deemed necessary by the Minister.