The daily report must contain all the elements applicable to the declared day, in particular,(1) the number of the geophysical surveying authorization;
(2) the type of surveying conducted and the energy sources used;
(3) a description, in chronological order, of the work carried out and the time required to carry out each step of the work;
(4) the number of the lines or traverses in which the data was acquired;
(5) the number of linear kilometres acquired or the area covered, their total and the remaining quantity;
(6) work interruptions and disturbances due, in particular, to meteorological conditions and technical and operational difficulties, and their duration;
(7) the operational problems encountered and the corrective measures taken or planned; and
(8) any other information or document deemed necessary by the Minister.