The daily report must contain all the elements that are applicable to the declared day including, in particular,(1) the number of the permanent closure authorization;
(2) a description, in chronological order, of the work carried out and the time required to carry out each step;
(3) the petroleum or water traces detected;
(4) the type of pump used and its capacity;
(5) the type of cement used, its density, its additives and their proportions, the setting time and the volume used;
(6) the well logs carried out;
(7) the results of the pressure and leak tests;
(8) the working condition of the blowout prevention system;
(9) the operational problems encountered and the corrective measures taken or planned;
(10) the composition, concentration and a detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(11) the volume and composition of the gas used, released, incinerated or burnt at the flare;
(12) the indication of any event that disrupted the progress of the work; and
(13) any other information or document deemed necessary by the Minister.