256. The authorization holder must notify the Minister, in writing, at least 14 days before the expected start date for the construction of the infrastructures necessary for the production and at least 30 days before the start date of the production.
Where the holder cannot comply with the start date, the holder must as soon as possible notify the Minister, in writing, indicating the reasons justifying the delay. The holder must also notify the Minister, in writing, of the new expected date for the start of the work if the date is expected within 14 or 30 days of the first notice of delay, as the case may be, or of the holder’s intent not to proceed.
1252-2018O.C. 1252-2018, s. 256.