64. Track surface must comply with the following requirements:(1) the runoff in any 9.45 m (31 ft.) of rail at the end of a raise may not be more than 8.89 cm (31/2 in.);
(2) the deviation from uniform profile on any rail at the mid-ordinate of an 18.9 m (62 ft.) chord may not be more than 7.62 cm (3 in.);
(3) deviation from designated elevation on spirals may not be more than 4.44 cm (13/4 in.);
(4) variation in cross level on spirals in any 9.45 m (31 ft.) may not be more than 5.08 cm (2 in.);
(5) deviation from zero cross level at any point on tangent or from designated elevation on curves between spirals may not be more than 7.62 cm (3 in.); and
(6) the difference in cross level between any 2 points less than 18.9 m (62 ft.) apart on tangents and curves between spirals may not be more than 7.62 cm (3 in.).