51. The Commission may require employers to send, before the beginning of the works or following such date, the following information in writing:(1) the date of the beginning of the work;
(2) the forecasted duration of the work;
(3) the address of the construction site;
(4) the estimate cost of the works;
(5) the type of construction;
(6) the quantity and type of workforce.