6. Every manager of a receiving site in which contaminated soils are discharged temporarily is required, before the soils may leave the site, to satisfy the requirements of section 12, with the necessary modifications.
If soils are returned to their site of origin by a receiving site manager, the recipient of the returned soils must, when they arrive, satisfy the requirements of section 19, with the necessary modifications.
Despite the first paragraph, if the receiving site manager refuses to receive contaminated soils, the requirements of the first paragraph must be satisfied by the recipient of the returned soils along with the requirements under the second paragraph.
The first paragraph does not apply if the receiving site is a ship or a train.
877-2021O.C. 877-2021, s. 6.