10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,459$1,459$1,459$1,459
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$7,297$25,547$43,795$62,048
Total with or without public hearing$8,756$27,006$45,254$63,507
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under Division III of Chapter II of Title II of the Act or the procedure under Division III of Chapter III of Title II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,459 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11; M.O. 2019-08-28, s. 7.
10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,444$1,444$1,444$1,444
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$7,222$25,284$43,344$61,409
Total with or without public hearing$8,666$26,728$44,788$62,853
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under Division III of Chapter II of Title II of the Act or the procedure under Division III of Chapter III of Title II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,444 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11; M.O. 2019-08-28, s. 7.
10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,417$1,417$1,417$1,417
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$7,085$24,804$42,522$60,244
Total with or without public hearing$8,502$26,221$43,939$61,661
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under Division III of Chapter II of Title II of the Act or the procedure under Division III of Chapter III of Title II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,417 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11; M.O. 2019-08-28, s. 7.
10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,417$1,417$1,417$1,417
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$7,085$24,804$42,522$60,244
Total with or without public hearing$8,502$26,221$43,939$61,661
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under subdivision 3 of Division II of Chapter II of the Act or the procedure under subdivision 3 of Division III of Chapter II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,417 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11.
10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,386$1,386$1,386$1,386
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$6,932$24,268$41,604$58,943
Total with or without public hearing$8,318$25,654$42,990$60,329
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under subdivision 3 of Division II of Chapter II of the Act or the procedure under subdivision 3 of Division III of Chapter II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,386 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11.
10.1. The following fees are payable by applicants for a certificate of authorization issued under section 160 or 196 of the Act, according to the rate class that applies to the project:
Steps in the environmental impact assessment and review procedureRate classes
1234
1. Transmission to the Minister of the preliminary information under section 156 of the Act$1,366$1,366$1,366$1,366
2. Impact statement under the second paragraph of section 160 and the first paragraph of section 196 of the Act$6,830$23,910$40,990$58,073
Total with or without public hearing$8,196$25,276$42,356$59,439
Schedule II determines the rate class for each class or subclass of projects listed in the Schedule.
If the application is for a project that is not listed in that Schedule but that is subject to the procedure under subdivision 3 of Division II of Chapter II of the Act or the procedure under subdivision 3 of Division III of Chapter II of the Act, the rate classes set out in Schedule III apply or, if the project is not listed in either Schedule II or Schedule III, the fees for class 1 are payable.
Fees of $1,366 are payable by an applicant for an attestation of exemption issued under paragraph b of section 154 or paragraph b of section 189 of the Act for a project not listed in either Schedule A or Schedule B to the Act or in Schedule III to this Order.
M.O. 2016, s. 11.