Type of amendment | Fees payable according to the class assigned to the project | |||||||
1 | 2 | 3 | 4 | |||||
Amendment to support documents or information already filed with an application and not involving capacity, production or a process change or having no environmental impact | $1,664 | $1,664 | $1,664 | $1,664 | ||||
Amendment involving capacity, a production increase or a process change | $4,992 | $15,398 | $25,804 | $36,210 | ||||
Rate for any other amendment | $3,329 | $11,652 | $11,652 | $11,652 |
Type of amendment | Fees payable according to the class assigned to the project | |||||||
1 | 2 | 3 | 4 | |||||
Amendment to support documents or information already filed with an application and not involving capacity, production or a process change or having no environmental impact | $1,589 | $1,589 | $1,589 | $1,589 | ||||
Amendment involving capacity, a production increase or a process change | $4,767 | $14,703 | $24,639 | $34,576 | ||||
Rate for any other amendment | $3,178 | $11,126 | $11,126 | $11,126 |
Type of amendment | Fees payable according to the class assigned to the project | |||||||
1 | 2 | 3 | 4 | |||||
Amendment to support documents or information already filed with an application and not involving capacity, production or a process change or having no environmental impact | $1,494 | $1,494 | $1,494 | $1,494 | ||||
Amendment involving capacity, a production increase or a process change | $4,484 | $13,803 | $23,176 | $32,523 | ||||
Rate for any other amendment | $2,990 | $10,465 | $10,465 | $10,465 |
Type of amendment | Fees payable according to the class assigned to the project | |||
1 | 2 | 3 | 4 | |
Amendment to support documents or information already filed with an application and not involving capacity, production or a process change or having no environmental impact | $1,494 | $1,494 | $1,494 | $1,494 |
Amendment involving capacity, a production increase or a process change | $4,484 | $13,803 | $23,176 | $32,523 |
Rate for any other amendment | $2,990 | $10,465 | $10,465 | $10,465 |