S-3.1.01 - Dam Safety Act

Full text
35.4. Any decision referred to in section 35.3 as well as any opposition to the transfer of an authorization or an approval provided for in section 12 may, within 30 days of its notification, be contested by the person concerned before the Administrative Tribunal of Québec.
The proceeding brought before the Tribunal does not suspend the execution of the decision unless, upon a motion heard and judged on an urgent basis, a member of the Tribunal orders otherwise by reason of urgency or of the risk of serious and irreparable injury.
If the Tribunal issues such an order, the proceeding shall be heard and judged on an urgent basis.
2022, c. 8, s. 159.