2120. The contractor, the architect, the engineer and the professional technologist, for the work they directed or supervised, and, where applicable, the subcontractor, for the work he performed, are jointly bound to warrant the work for one year against poor workmanship existing at the time of acceptance or discovered within one year after acceptance.
1991, c. 64, a. 2120; 2002, c. 19, s. 15; I.N. 2014-05-01; 2020, c. 15, s. 59.
2120. The contractor, the architect and the engineer, for the work they directed or supervised, and, where applicable, the subcontractor, for the work he performed, are jointly bound to warrant the work for one year against poor workmanship existing at the time of acceptance or discovered within one year after acceptance.
1991, c. 64, a. 2120; 2002, c. 19, s. 15; I.N. 2014-05-01.
2120. The contractor, the architect and the engineer, in respect of work they directed or supervised, and, where applicable, the subcontractor, in respect of work he performed, are jointly liable to warrant the work for one year against poor workmanship existing at the time of acceptance or discovered within one year after acceptance.
1991, c. 64, a. 2120; 2002, c. 19, s. 15.
2120. The contractor, the architect and the engineer, in respect of work they directed or supervised, and, where applicable, the subcontractor, in respect of work he performed, are solidarily liable to warrant the work for one year against poor workmanship existing at the time of acceptance or discovered within one year after acceptance.