895. (Repealed).
1920, c. 83, s. 1; 1999, c. 40, s. 60; 2005, c. 6, s. 214.
895. (1)  The owner or occupant of any immovable property who is about to commence or has commenced the construction of a ditch, for the purpose mentioned in article 894, shall be bound to notify, in writing, every owner or occupant of immovable property who will be affected by the proposed works, and to call them together to discuss the project.
(2)  The time allowed by the notice must be seven clear days, from the mailing of the notice or from its delivery by hand to the day fixed by the notice for the meeting.
(3)  Such notice must contain the date, place and hour of the meeting, as well as the nature, extent and probable cost of the proposed work, and, according to their respective interests therein, the share to be borne by each interested party, the work he must do, and the material he must supply.
1920, c. 83, s. 1; 1999, c. 40, s. 60.
895. (1)  The owner or occupant of any immovable property who is about to commence or has commenced the construction of a ditch, for the purpose mentioned in article 894, shall be bound to notify, in writing, every owner or occupant of immovable property who will be affected by the proposed works, and to call them together to discuss the project.
(2)  The delay allowed by the notice must be seven clear days, from the mailing of the notice or from its delivery by hand to the day fixed by the notice for the meeting.
(3)  Such notice must contain the date, place and hour of the meeting, as well as the nature, extent and probable cost of the proposed work, and, according to their respective interests therein, the share to be borne by each interested party, the work he must do, and the material he must supply.