C-65.1, r. 1.1 - Regulation respecting supply contracts, service contracts and construction contracts of bodies referred to in section 7 of the Act respecting contracting by public bodies

Full text
1.10. If, 2 days before the tender closing date, the body has not indicated on the electronic tendering system that it has sent its decision on a complaint, the system operator must, without delay, defer the tender closing date by 4 days.
If the deferred date falls on a holiday, it must again be deferred to the second next working day. If the day preceding the deferred date is not a working day, that date must be deferred to the next working day.
S.Q. 2017, c. 27, s. 229.
Not in force
1.10. If, 2 days before the tender closing date, the body has not indicated on the electronic tendering system that it has sent its decision on a complaint, the system operator must, without delay, defer the tender closing date by 4 days.
If the deferred date falls on a holiday, it must again be deferred to the second next working day. If the day preceding the deferred date is not a working day, that date must be deferred to the next working day.
S.Q. 2017, c. 27, s. 229.