Q-2, r. 0.1 - Regulation respecting activities in wetlands, bodies of water and sensitive areas

Full text
39. Work aimed at constructing an artificial basin, pond or lake must not include an intake channel or a discharge point in another wetland or body or water. Work undertaken to backfill such an area may not be carried out until after the area has been dewatered.
871-2020O.C. 871-2020, s. 39.
In force: 2020-12-31
39. Work aimed at constructing an artificial basin, pond or lake must not include an intake channel or a discharge point in another wetland or body or water. Work undertaken to backfill such an area may not be carried out until after the area has been dewatered.
871-2020O.C. 871-2020, s. 39.