S-2.1 - Act respecting occupational health and safety

Full text
209. Where it is foreseen that activities on a construction site will occupy at least 10 construction workers simultaneously at a stage of the work, at least one health and safety representative must be designated, as soon as work begins, by a majority of the construction workers present on the construction site.
Failing that, the representative association with the most affiliated construction workers present on the construction site shall designate the health and safety representative.
1979, c. 63, s. 209; 2021, c. 27, s. 226.
Not in force
209. Where it is foreseen that activities on a construction site will occupy at least 10 construction workers simultaneously at a stage of the work, at least one health and safety representative must be designated, as soon as work begins, by a majority of the construction workers present on the construction site.
Failing that, the representative association with the most affiliated construction workers present on the construction site shall designate the health and safety representative.
1979, c. 63, s. 209; 2021, c. 27, s. 226.
Not in force
209. A representative association may designate one or more persons to be safety representatives on a construction site where a construction worker who is a member of a union or of an association of employees affiliated to the representative association is working.
Persons designated under this section must be construction workers working on the construction site.
1979, c. 63, s. 209.