Q-2 - Environment Quality Act

Full text
65.3. If a study required under section 65 reveals the presence of residual materials at the property line of the land, a migration of gas outside the land or a serious risk of such migration, the person that conducted the study is required to notify the owner of the neighbouring land concerned in writing without delay. A copy of the notice must also be sent to the Minister.
2017, c. 4, s. 111; 2022, c. 8, s. 137.
65.3. If a study required under section 65 reveals the presence of residual materials at the property line of the land, a migration of gas outside the land or a serious risk of such migration, the person or municipality that conducted the study is required to notify the owner of the neighbouring land concerned in writing without delay. A copy of the notice must also be sent to the Minister.
2017, c. 4, s. 111.