79.1. Every contractor required to join a guaranty plan under section 77 or 78 is bound to repair any defect in construction resulting from the failure to carry out or from the carrying out of construction work covered by the plan. The contractor must also, where applicable, complete the carrying out of the work or pay the compensation prescribed by regulation of the Board.
Should the contractor fail to repair such defects and, where applicable, to complete the work or pay the compensation, the manager of the plan shall make the repairs and, where applicable, complete the work or pay the compensation.
1995, c. 58, s. 4.