A-19.1 - Act respecting land use planning and development

Full text
148.0.23. Throughout the demolition work, a copy of the authorization certificate must be in the possession of a person in authority on the premises. A municipal officer designated by the council may enter the premises where the work is being carried out at any reasonable time to ascertain whether the demolition is in conformity with the committee’s decision. On request, the officer must provide identification and produce a certificate issued by the municipality attesting the authority vested in the officer.
A person who
(1)  refuses to allow a municipal officer on the premises where the demolition work is being carried out; or
(2)  is the person in authority responsible for the demolition work and who, on the premises where the demolition work is to take place, refuses to show a municipal officer a copy of the authorization certificate
is liable to a fine not exceeding $500.
2005, c. 6, s. 134.