R-6.01, r. 5.1 - Regulation respecting the annual contribution payable to Energy Transition Québec

Full text
7. Any balance unpaid by the energy distributor on the due date bears interest at the rate determined pursuant to section 28 of the Tax Administration Act (chapter A-6.002). The interest is capitalized monthly.
In addition to the interest payable, a penalty of 15% is added to any sum owing if the delay exceeds 60 days. In no case may the amount of the penalty exceed 15% of the amount that should have been paid.
1150-2018O.C. 1150-2018, s. 7.
In force: 2018-09-13
7. Any balance unpaid by the energy distributor on the due date bears interest at the rate determined pursuant to section 28 of the Tax Administration Act (chapter A-6.002). The interest is capitalized monthly.
In addition to the interest payable, a penalty of 15% is added to any sum owing if the delay exceeds 60 days. In no case may the amount of the penalty exceed 15% of the amount that should have been paid.
1150-2018O.C. 1150-2018, s. 7.